Details of Contract awarded for the value of above Rs.1 crore. |
|
Sl. No. |
Tender NoticeNo. |
Item/Nature of Work |
Mode of Tender enquiry |
Date of Publication of NIT |
Type of bidding (Single/two bid system) |
Last date of receipt of Tender |
Nos. of Tender received |
Nos. and name of parties qualified after technical evaluation |
Nos. & names of Parties not qualified after technical evaluation |
Whether contract awarded to lowest tenderer/ Evaluated L1 |
Contract No. & date |
Name of contractor |
Value of contract |
Scheduled date of completion of supplies |
Reasons for delays, if any |
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 |
| 3 |
DRM(Engg)/RNC/ 25/05 dt.24.11.05
|
OT for Supply and loading into Railway wagon/hoppers 75000 cum 50 mm gauge machine crushed hard stone track ballast at Rajgram for Ranchi division.. | Open Tender | 30.11.1005 | Single | 30.12.05 | 2 | S.B.D. Enterprise | Nil | Yes |
TB/01/2006/OT Dt.05.07.06
|
S.B.D. Enterprise | 3,25,64,648/- | 04.10.2007 | |
| 2 |
DRM(Engg)/RNC/ 27/04 dt.30.09.04 |
OT for complete Track renewal(S) on loop lines with 52 kg SH rail on New/SH PSC sleeper/pad plated IRS sleeper between MURI-HTE for 23 km under ADEN/RNC. | Open Tender | 08.10.2004 | Single | 10.11.04 | 2 | 2 Bhrigujee Construction | Nil | Yes |
TB/84/04/OT Dt.25.07.05
|
Bhrigujee Construction | 1,30,01,614/- | 24.06.06 | |
|
1 |
DRM(Engg)/RNC/ 24/04 dt.11/08/04. |
Supply and loading into Railway wagons/hoppers 50000 cum at Rajgram for Ranchi division. |
Open Tender |
21.08.2004 |
Single |
22.09.04 |
2 |
2 Ramesh Kumar Bhawnani, Raghu Stone Works |
Nil |
Yes |
TB/76/04/OT Dt.04.02.05 |
Ramesh Kumar Bhawnani |
2,02,89,500/- |
03.08.05 |
|